Quick Reference Chart:
When a Permit is Required:
Within 10m Meter Safety Corridor
All Activities (including all Encroachments, Seismic, Drilling Wells,
and Residential Dwellings)
A TransGas Representative must
witness the work
Within 30m Encroachment Permitting Area
All Activities (Ground Disturbance with 30m)
Example:
-
Hunting Pit - Burying a Rock Pile - Fence
-
Pipe Replacement - Test Hole Drilling - Foundations
-
Buildings - Dugouts - Poles/Posts (for signage)
-
Installation, Maintenance or Removal of Pipelines, Power Lines, Cables, Power Poles,
and Roads or Ditches that Parallel or Cross a TransGas Pipeline
-
V-Ditching
Within 40m Seismic Permitting Area
**40m from edge of R.O.W. for MIPL(C) Lines All Seismic Activity
Within 75m Well Drilling Permitting Area
Well Drilling (includes oil, gas, water, piezometers, and bore holes)
Within 200m Residential Dwelling Monitoring Area
(No Permit Issued)
Notify Crossing Coordination - Class Location Survey
Contact Crossing Coordination @ 306-777-9666
Fax 306-777-9146
Email: engfax@transgas.com
|