My TransGas (QPTM)
Planned Outages

The Planned Outage Report provides the date and duration of planned TransGas work which will result in a partial or full interruption of receipt and delivery service to customers. This report is intended to provide an early notice to customers to help in the planning of their own facility maintenance work. This summary excludes planned outages that are scheduled during customer planned shutdowns. Where possible, TransGas will work with customers to minimize the outage impact, and schedule the planned TransGas work to coincide with customer maintenance or downtime. Please contact your Key Account Manager for further information.

Click for map view

REMAINING 2017 OUTAGES IMPACTING CUSTOMERS
Published Date: 14 September 2017 08:00 am

#

PROJECT
DURATION
(Days)
START
DATE
CAPACITY
AVAILABLE
RECEIPT CUSTOMERS
AFFECTED
DELIVERY CUSTOMERS
AFFECTED
1 Reduced Pressure Operation 4 September 14 0% Meter #4507  
2 Facility Improvements 5 September 15 0% Meter #1726  
3 System Integrity Modifications 2 September 18 0% Meter #6273  
4 System Integrity Modifications 4 September 19 0%   Meter #6702, #7102, #7720
5 System Integrity Modifications 2 September 20 0% Meter #3016, #6273  
6 Facility Improvements 4 September 26 0%   Meter #7736, #7780
7 Facility Improvements <1 October 3 0% Meter #3030  
8 Required Pipeline Modification 2 October 3 0% Meter #4535, #4720, #6293 Meter #1717
9 Facility Improvements 1 October 10 0%   Meter #1690
10 Facility Improvements 2 October 11 0% Meter #1667, #6332, #6333  
11 System Integrity Modifications 2 October 12 0% Meter #2514  
12 System Integrity Modifications 2 October 17 0%   Meter #7710
13 System Integrity Modifications 2 October 18 0% Meter #2508  
14 System Integrity Modifications 2 October 25 0% Meter #2512  
15 System Integrity Modifications 1 October 26 0% Meter #4672 Meter #1699, #1719
16 System Integrity Modifications 1 October 0% Meter #2510  
17 Facility Improvements 1 November 0% Meter #4666, #1685  
18 Facility Improvements <1 November 0% Meter #6253  
19 Facility Improvements <1 November 0% Meter #4654  